Air source heat pumps
Low-carbon heating and hot water, with new copper distribution throughout.
Discuss M&EThe Project
A complete internal and external refurbishment of an established Croydon hotel, delivered under C1 consent with an entirely new services, fire safety, and fit-out package.
7 Altyre Road, Croydon CR9 5AA
C1 (hotel) planning consent
Amro Flemyn
3 January 2026 - 19 December 2026 (12 months)
Month 9 of 12 delivered: ground-floor amenity and landscaping to follow
Baileys Building Contractors
Site Establishment & Scaffolding
Baileys Building Contractors managed the comprehensive internal and external refurbishment of Croydon Park Hotel under C1 planning consent.
Initial site mobilisation established full perimeter access scaffolding, heavy-duty concrete plant bases, and safe working access across all levels before structural strip-out and service installation commenced.
See what you gain by working with us. Six concrete benefits that set us apart from the rest.
All terms clear from day one. No hidden costs or vague clauses.
Regular photos and updates, so you always know where the project stands.
You pay for work actually completed, not upfront for the whole project.
A realistic deadline written into the contract. Your time matters.
One person manages the project from start to finish. You always know who to talk to.
We help spread the investment into convenient installments that fit your budget.
Started 3 January 2026, completing 19 December 2026. Months 1 to 9 delivered; the final three complete the ground floor and landscaping.
Site set up, full perimeter scaffold erected, and reinforced concrete bases formed and poured for new external plant. Fit-out began on the first rooms to establish the finish standard.
Enquire with Baileys
Bedrooms stripped back to structure and bathroom risers opened up. A completed model room set the benchmark for every room that followed.
Enquire with Baileys
Through-wall MVHR units installed beside each window, with new insulation and a fully taped vapour control layer. New soil stacks and copper pipework ran through the risers.
Enquire with Baileys
New cable tray and containment along the corridors, with air-conditioning units and refrigerant pipework installed at high level. Dry-lining progressed and moisture-resistant boards went into the en-suites.
Enquire with Baileys
New sprinkler mains and heads installed to rooms and corridors. En-suite tiling started, and over-cladding of the existing roof began.
Enquire with Baileys
Bespoke joinery went in: kitchenettes, slatted feature walls and bed bases, with LVT flooring laid. Ground-floor partitions rose around the central atrium.
Enquire with Baileys
New anthracite roof sheeting completed across the main roof. A new sectional water tank was installed in the roof plant space, and ventilation ductwork ran through the ground floor.
Enquire with Baileys
A new substation was installed for the all-new power supply, and copper heating and cooling distribution was completed. Corridors were finished with porcelain tiling and feature ceilings.
Enquire with Baileys
Bedroom floors dressed and complete, en-suites finished, and the facade and roofs signed off, including a new liquid-applied membrane to the lower roof.
Enquire with BaileysNext Phase (October - December 2026)
The final three months complete the ground-floor amenity spaces around the central atrium and the external landscaping, ready for handover.
This case study documents works delivered through September 2026 (Month 9 of 12). Ground-floor amenity construction and external landscaping are currently underway.
Building Services & Fire Safety
A complete mechanical, electrical, and fire safety package delivered to modern commercial standards.
Low-carbon heating and hot water, with new copper distribution throughout.
Discuss M&E
Heat-recovery ventilation to every room, sealed into the new envelope.
Discuss M&ENew substation feeding fresh electrical distribution and containment.
Discuss M&E
New mains, valves, and heads to bedrooms, corridors, and public areas.
Fire safety specsCompartmentation renewed and every new service penetration sealed.
Fire safety specs
From Month 03 bare shell strip-out to Month 09 finished, dressed guest studios and completed building envelope.