Finished executive hotel bedroom refurbishment at Croydon Park Hotel
Commercial Refurbishment Case Study

Croydon Park Hotel

A 12-month refurbishment creating a fully serviced, fire-protected and finished hotel (nine months delivered to date).

  • Delivered under C1 planning consent
  • Full mechanical & electrical package
  • Comprehensive fire stopping

The Project

Commercial hotel refurbishment delivered under C1 planning consent

A complete internal and external refurbishment of an established Croydon hotel, delivered under C1 consent with an entirely new services, fire safety, and fit-out package.

Location

7 Altyre Road, Croydon CR9 5AA

Planning Consent

C1 (hotel) planning consent

Client

Amro Flemyn

Programme

3 January 2026 - 19 December 2026 (12 months)

Current Status (September 2026)

Month 9 of 12 delivered: ground-floor amenity and landscaping to follow

Contractor

Baileys Building Contractors

Site Establishment & Scaffolding

Complete structural
and envelope overhaul

Baileys Building Contractors managed the comprehensive internal and external refurbishment of Croydon Park Hotel under C1 planning consent.

Initial site mobilisation established full perimeter access scaffolding, heavy-duty concrete plant bases, and safe working access across all levels before structural strip-out and service installation commenced.

Croydon Park Hotel exterior scaffolding and access works

Why choose us?

See what you gain by working with us. Six concrete benefits that set us apart from the rest.

Transparent contracts

All terms clear from day one. No hidden costs or vague clauses.

Progress reports

Regular photos and updates, so you always know where the project stands.

Stage payments

You pay for work actually completed, not upfront for the whole project.

Deadline in contract

A realistic deadline written into the contract. Your time matters.

Dedicated project supervisor

One person manages the project from start to finish. You always know who to talk to.

Financing

We help spread the investment into convenient installments that fit your budget.

The Programme So Far: Months 01 to 09

Started 3 January 2026, completing 19 December 2026. Months 1 to 9 delivered; the final three complete the ground floor and landscaping.

Month 01 (January 2026): Mobilisation & enabling works

Month 01 (January 2026): Mobilisation & enabling works

Site set up, full perimeter scaffold erected, and reinforced concrete bases formed and poured for new external plant. Fit-out began on the first rooms to establish the finish standard.

Enquire with Baileys
Month 02 (February 2026): Strip-out & model room

Month 02 (February 2026): Strip-out & model room

Bedrooms stripped back to structure and bathroom risers opened up. A completed model room set the benchmark for every room that followed.

Enquire with Baileys
Month 03 (March 2026): Envelope, insulation & MVHR

Month 03 (March 2026): Envelope, insulation & MVHR

Through-wall MVHR units installed beside each window, with new insulation and a fully taped vapour control layer. New soil stacks and copper pipework ran through the risers.

Enquire with Baileys
Month 04 (April 2026): M&E distribution

Month 04 (April 2026): M&E distribution

New cable tray and containment along the corridors, with air-conditioning units and refrigerant pipework installed at high level. Dry-lining progressed and moisture-resistant boards went into the en-suites.

Enquire with Baileys
Month 05 (May 2026): Sprinklers, wet rooms & roof

Month 05 (May 2026): Sprinklers, wet rooms & roof

New sprinkler mains and heads installed to rooms and corridors. En-suite tiling started, and over-cladding of the existing roof began.

Enquire with Baileys
Month 06 (June 2026): Joinery, flooring & ground floor

Month 06 (June 2026): Joinery, flooring & ground floor

Bespoke joinery went in: kitchenettes, slatted feature walls and bed bases, with LVT flooring laid. Ground-floor partitions rose around the central atrium.

Enquire with Baileys
Month 07 (July 2026): Roof completion & plant

Month 07 (July 2026): Roof completion & plant

New anthracite roof sheeting completed across the main roof. A new sectional water tank was installed in the roof plant space, and ventilation ductwork ran through the ground floor.

Enquire with Baileys
Month 08 (August 2026): Power, pipework & corridors

Month 08 (August 2026): Power, pipework & corridors

A new substation was installed for the all-new power supply, and copper heating and cooling distribution was completed. Corridors were finished with porcelain tiling and feature ceilings.

Enquire with Baileys
Month 09 (September 2026): Rooms & envelope complete

Month 09 (September 2026): Rooms & envelope complete

Bedroom floors dressed and complete, en-suites finished, and the facade and roofs signed off, including a new liquid-applied membrane to the lower roof.

Enquire with Baileys

Next Phase (October - December 2026)

Ground-floor amenity
and external landscaping

The final three months complete the ground-floor amenity spaces around the central atrium and the external landscaping, ready for handover.

This case study documents works delivered through September 2026 (Month 9 of 12). Ground-floor amenity construction and external landscaping are currently underway.

Ground floor central atrium construction at Croydon Park Hotel

Building Services & Fire Safety

Engineered M&E strategy and fire protection

A complete mechanical, electrical, and fire safety package delivered to modern commercial standards.

Air source heat pump copper pipework installation

Air source heat pumps

Low-carbon heating and hot water, with new copper distribution throughout.

Discuss M&E

Air conditioning

Comfort cooling with indoor units and refrigerant runs at high level.

Discuss M&E
Air conditioning refrigerant lines
MVHR heat recovery ventilation unit

Through-wall MVHR

Heat-recovery ventilation to every room, sealed into the new envelope.

Discuss M&E

All-new power supply

New substation feeding fresh electrical distribution and containment.

Discuss M&E
Substation and power containment
Fire sprinkler pipework and heads

New sprinkler installation

New mains, valves, and heads to bedrooms, corridors, and public areas.

Fire safety specs

Fire stopping & protection

Compartmentation renewed and every new service penetration sealed.

Fire safety specs
Fire stopping and compartmentation sealing

Built by Baileys

Planning, services, fire safety and fit-out: managed as one package from strip-out to handover.